Feb. 2004 – Initial discussion starts
Sept. 2004 – It becomes clear that there is no contingency money for the shop.  Let’s build it anyway!
March 2005 – The county decides we need to have a bathroom in the shop before they’ll approve our plans.  We appeal to the appeals board.
May 2005 – We get permission to build the workshop without a bathroom, and can build it largely ourselves.
Fall 2005 – Design, including evaluating SIP (structural insulated panels).
March 2006 – Final design completed, quotes from various suppliers.
May 2006 – Building permit issued!
July 3, 2006 – Building begins.  Site is cleared, work on removing curb begins.
Sept. 2006 – SIP panels ordered.  Footings dug.
October 2006 – Footings poured.  Foundation blocks.  SIP panels arrive.  Walls are up by the end of October. 
Nov. 2006 – Windows on site.  Trusses installed.
Dec. 2006 – Roof done.  Floor poured.
Feb. 2007 – Garage door installed.
May 2007 – Concrete curb remains trucked off.
June 2007 – Siding, continuing through October 1.
Jan. 2008 – Electrical and lighting planning.
Spring 2008 – Interior wall installed. (?)
June-Dec. 2008 – Rough electrical work.
March 2009 – Drywall (walls and ceiling)
June 1, 2009 – Electrical final inspection passed.
Aug. 17, 2009 – Workshop Committee Mandate approved.
Sept. 1, 2009 – Gas finally hooked up (started in Jan. 2009)
Sept. 21, 2009 – Overall Community Workshop Policy adopted
Oct. 8, 2009 – Final inspection passed.
Jan. 31, 2010 – Open House!